We’re implementing Map for Mobile, our community-wide plan for growth.
Learn about the City’s plans and get involved in efforts to make Mobile a great place to live, work and raise a family.
Projects and Plans Underway
Zoning Code (UDC)
Status
Ongoing- NextThe City will convene a public work session to gather input to improve the Downtown Development District (DDD) code. Wednesday September 3, 6 pm at Gulfquest
Updated Aug 14, 2026
Broad Street and MLK Jr Avenue
Status by phase
1234
- 1Canal to Lawrence St Complete
- 2Canal to Lawrence St Complete
- 3Canal to Baker Design90% design plans in review
- 4MLK Ave: Broad to Butchers Ln ConstructionLane closures currently run from Butchers Lane to Davidson Street. Waterline has been installed to Monday Street and is expected to be completed by the end of the summer at Broad Street. Work continues behind the waterline with curb, inlets, sidewalks and lighting and drainage improvements.
Updated Aug 14, 2026
Cooper Riverside Park
Status by phase
12
- 1Shoreline Stabilization CompleteInstallation of new bulkhead structure along the Great Lawn areas. (Completed May 2025) Installation of new bulkhead structure along South Coffer Cell area. (Completed December 2025)
- 2Upland Enhancements ConstructionImprovements to the Great Lawn area by enhancing upland amenities, landscaping, hardscaping, and infrastructure, to enhance the park’s functionality, aesthetics, safety, and overall visitor experience. (Construction is 95% complete with final items funded)
Updated Aug 12, 2026
Three Mile Creek Greenway Trail
Status by segment
1234567
- 1Japanese Gardens Complete
- 2Forest Hill Design
- 3Moffett Rd Connector Design
- 5Bush Park to Mill Street Park DesignRecently completed four real estate transactions to secure right-of-way
- 6University Hospital Connector Complete
- 7MLK Jr Ave Connector DesignAwaiting a notice to bid from RESTORE
Updated Aug 13, 2026
Three Mile Creek Watershed Restoration (Langan Lake Dredging)
Status by phase
123
- 1Twelve Mile Creek Bank Stabilization University Blvd to Museum Drive Complete
- 2Twelve Mile Creek Bank Stabilization East Drive to University Blvd Complete
- 3Langan Lake Dredging Construction
Updated Aug 14, 2026
Brookley By The Bay
Status by phase
123
- 1Active Shoreline Design100% construction documents completefor Park Phase 1. This phase will include two age-specific play areas, an experiential water play area, pavilions, parking, restrooms, exercise paths, BBQ stations, and fresh plantings to help Mobilians feel closer to nature.
- 2Ampitheater Design
- 3Education Center Design
Updated Aug 14, 2026
Map for Mobile and Future Land Use Plan
Capital Improvements Plan
Status
Ongoing- Next2027-2031 CIP is in final review
Updated Aug 14, 2026